REASONS FOR THE INCREASE OF EFFECTIVE ELECTRICITY RATES IN MAINLAND AND BAPA (ON-GRID) CONSUMERS FOR THEM ONTH OF JUNE 2024



1. Increase of Purchased Power for the Month of May 2024.

The cost of power purchased from power plants significantly increased proportionately from Php 158,330,634.99 with kWh 20,101,961.62 for the month of April 2024 to Php 172,875,380.35 with kWh of 14,544,745.35, resulted to an increase of generation cost by Php 0.6306 per kWh.

Factors affecting the increase of COST OF POWER.

a. Increase in Exposure to WESM and Utilization of Bunker/Diesel Power Plant of NAC due to the increase of SURNECO COINCIDENT PEAK DEMAND.
Other source of power other than the Independent Power Producers and NPC/PSALM is the Wholesale Electricity Sport Market (WESM), wherein SURNECO may opt to buy electricity in lieu of the contracted power plants. The total contracted demand as implemented for the month billing month of May 2024 is only 33.4 mW. However, the actual Coincident Peak Demand of SURNECO as of May 2024 reaches to 39.5 mW. The shortage of 6.1 megawatt was sourced out from WESM with electricity rates cap at Php 32.00 per kwh. Also, SURNECO has activated the embedded generation of Nickel Asia Corporation(NAC) with high fuel cost.

b. Increase in Fuel Cost Rate
Majority of the contracted Power Supply are fueled by Coal, and Bunker/Diesel. This makes SURNECO highly vulnerable to any price increase on imported fuel as it is one of the variable power costs that directly affects any changes in effective generation rate of SURNECO for having direct proportional relationship between fuel cost and effective billing rate..

2. Implementation of the 2023 FIT-ALL Rate in accordance with the ERC decision for ERC case no. 2022-051 RC.
In accordance with the ERC decision for ERC case no. 2022-051 RC (2023 FIT-ALL Rate Application filed by TRANSCO), the implementation to collect the CY 2023 FIT-ALL rate of Php 0.0838 per kWh shall start in the billing month of June 2024.

๐—ฅ๐—˜๐—”๐—ฆ๐—ข๐—ก๐—ฆ ๐—™๐—ข๐—ฅ ๐—ง๐—›๐—˜ ๐—ก๐—˜๐—ง ๐——๐—˜๐—–๐—ฅ๐—˜๐—”๐—ฆ๐—˜ ๐—ข๐—™ ๐—˜๐—™๐—™๐—˜๐—–๐—ง๐—œ๐—ฉ๐—˜ ๐—˜๐—Ÿ๐—˜๐—–๐—ง๐—ฅ๐—œ๐—–๐—œ๐—ง๐—ฌ ๐—ฅ๐—”๐—ง๐—˜๐—ฆ ๐—œ๐—ก ๐— ๐—”๐—œ๐—ก๐—Ÿ๐—”๐—ก๐—— (๐—ข๐—ก-๐—š๐—ฅ๐—œ๐——) ๐—–๐—ข๐—ก๐—ฆ๐—จ๐— ๐—˜๐—ฅ๐—ฆ ๐—™๐—ข๐—ฅ ๐—ง๐—›๐—˜ ๐— ๐—ข๐—ก๐—ง๐—› ๐—ข๐—™ ๐——๐—˜๐—–๐—˜๐— ๐—•๐—˜๐—ฅ ๐Ÿฎ๐Ÿฌ๐Ÿฎ๐Ÿฏ



1). Decrease of Purchased Power for the month of July 2023.
30 out of 41 MW Contracted Power Supply Capacity of SURNECO is Coal Based. Making SURNECO highly vulnerable to any price increase on Fuel Cost. And it is one of the variable power costs that directly affects any changes in effective generation rate of SURNECO. Having direct proportional relationship between fuel cost and effective billing rates, any decrease in fuel cost will result to possible decrease in generation rate.

2. Previous Month Fuel Cost Bill Adjustment by Nickel Asia Corporation.
Last Month, Nickel Asia Corporation made a correction of error on fuel cost computation for the month of August and September 2023 resulting to an adjustment amounting to Php 5,478,606.71 that form part of October 2023 Power Bill and Increase the blended generation cost for the billing month of November 2023. Hence this month such adjustment was not part of the blended generation cost that attribute to over-all decrease in generation cost for the billing month of December 2023.

3. Decrease in Average Cost per KwH on WESM Transaction
Cost of Power in SURNECO WESM Transaction decreased from an average cost Php 6.2974 per kwh for the month of October 2023 to Php 5.1374 per kwh for the month of November 2023. This one of the factors that decrease the blended generation cost for the billing month of December 2023.

Contact Us

Main Office:

ย Espina Street, Surigao City
ย Hotline No.: 162
ย (086) 826-5456
ย 09195206025 / 09209765105
ย surneco_surigao@yahoo.com

ย 

ย Sub Offices:

SAO1- San Isidro, Gigaquit ย 09209459526
SAO2- Magpayang, Mainit ย 09209459475
SAO3- Malimono ย 09209459476
SAO4- Sta. Cruz, Placer ย 09209459483